Tampa - Hivelocity Generator Maintenance

Scheduled Maintenance Report for LevelOneServers

Completed

The scheduled maintenance has been completed.
Posted Sep 22, 2025 - 19:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 22, 2025 - 12:00 UTC

Scheduled

A message we received from Hivelocity:

We are writing to inform you our previously scheduled maintenance window has been rescheduled for 09/23/2025, from 8AM to 3PM EST to conduct preventative maintenance and testing on our generator systems within Tampa 2 (TPA2).

What is Happening?
This maintenance will require generator redundancy to be temporarily reduced for the duration of the window. This is part of our routine efforts to ensure the continued reliability and performance of critical infrastructure.

Maintenance Details:
-----------------------------
Date: 09/23/2025
Location: TPA2
Time: 8AM - 3PM EST
Duration: Approximately 7 hours

Impact on Services:
No service interruption is expected. Redundancy will be reduced during this window.
Posted Sep 19, 2025 - 15:55 UTC
This scheduled maintenance affected: tpa.hv (r01.tpa.hv, r02.tpa.hv).